As the main raw material,gypsum powder is transported to dosing system by screw conveyor. And then it flows into mixer after dosing system weighs gypsum powder each time. Inside the mixer,certain amount of water&other admixture are agitated and become slurry.
The surry is then poured into mould cavity of forming machine. After intial setting time,top tenon of a block is cleaned with the help of a surry scratching device. Afater finial setting time ( about 8 min) hydraulic lifing device(ejector mechanism) will take blocks onto trolleys,then trolleys are moved to change its transport direction through zone #1and pushed into drying kiln for drying the wet gypsum block. After those blocks become dry,they are moved to unloading clamp through direction changing zone 2#,where packed and sent to storge area. The empty trolleys are then moved back