Product Main

Quick Details

Condition: New
Place of Origin: China (Mainland)
Brand Name: Morgan
Model Number: MG-10
Use: Waste Plastic Crusher
Plastic Type: PP/PE
Shaft Design: Double
Power: 20W
Capacity:
Voltage: 220V,380V,440V
Power(W): 20
Dimension(L*W*H): 6600*2800*2800mm
Weight: 40T
Certification: CE,SGE,ISO
After-sales Service Provided: Engineers available to service machinery overseas
Application: Turn waste plastic to oil
Business Type: Manufacturer
Year Established: 1985
Experience: 20 years experience in this field
Daily profit: 1200 USD
Certification: CE&SGS&ISO9001
Raw material: waste, tire and plastic
End product: fuel oil.carbon black, steel wire
Warranty: 1 year
Welding times: 4
Welding Test: X-ray test
Delivery time: 30days after deposit

Specifications

About our company
We are specialized in manufacturing waste tire, plastic & rubber pyrolysis machine & distillation oil equipment, incidental tyre cut machine, carbon black refining machine and Carbon black granulator machine according to the market and customer requirements. With advanced production technology, high quality product, excellent sales and good after service our products are sold both in domestic and international market.
 
Oil refining machine working process:
Firstly,we put raw materials into reactor by auto-feeder, then heat the reactor with coal/ wood/natural gas / oil. when the temperature reach around 160 degree Celsius, oil gas will produce.
Secondly, liquid oil will be cooled out by cooling system from oil gas,which is collected by oil tank. 
Thirdly, the waste gas which can not be cooled out in normal pressure will be recycled to heat reactor,not only saving energy, but also protecting environment. 
Fourthly, the black smoke produced by heating reactor can achieve national emission standard through dual depressurization and dusting removal device.
 Fifthly, the temperature of reactor will be low after we get oil, at this moment carbon black will be discharged automatically. 
Lastly, when the temperature falls to 50 degree Celsius, worker could put steel wire hook to reactor to take steel wire out, then another batch will be begin. 
 
1.Oil refining machine model and capacity:
 
Reactor size
Weight
Volume
Capacity
Note
1
2200*6000mm
27MT
23 m³
5 MT
3 batches 2days
2
2200*6600mm
29MT
25 m³
6 MT
3 batches 2days
3
2600*6000mm
32MT
32 m³
8 MT
1 batch 1 day
4
2600*6600mm
34MT
35 m³
9 MT
1 batch 1 day
5
2800*6000mm
35MT
37 m³
10 MT
1 batch 1 day
6
2800*6600mm
38MT
41 m³
12 MT
1 batch 1 day
 
2.Oil refining machine of Fuels
The fuel can be fuel oil, heavy oil, coal& firewood.
 
3.Oil refining machine processing time:
Model
Feeding
Processing
Cooling
Discharge
total
2200*6000
2hr
7-8hr
2hr
2hr
14hr
2200*6600
2hr
8hr
2hr
2hr
14hr
2600*6000
3 hr
10 hr
3 hr
3 hr
19 hr
2600*6600
3 hr
11 hr
3 hr
3 hr
20 hr
2800*6000
3 hr
12 hr
3 hr
3 hr
21 hr
2800*6600
3 hr
13-14 hr
3 hr
3 hr
23 hr
 
4.Oil refining machine end product percentage (the raw material is tyre)
No
     Name
Percentage
Usage
1
Tyre oil
42%-45%
*can be sold directly
*make diesel and gasoline through oil distillation machine
*can be fuel
2
Carbon black
32%-35%
*fine carbon through grinding machine
*carbon rod through carbon pellet machine
*can be sold directly
3
Steel wire
12%-15%
*can be sold directly; 
*make steel bloom through hydraulic press-packing.
4
Oil gas
5%
*can heat the reactor as fuel
 
5. Oil refining machine motor power
  System
Components 
    Power
Pyrolysis system
Screw conveyor
   4 kw / h
Reactor
   4 kw / h
Cooling system
Cooling tower
  4 kw / h
Waste gas recycle   
    system
Blower
  0.75 kw / h
Exhaust disposal system 
Draft fan
   7.5kw / h
 
6.Oil refining machine packing containers:
2200*6000
two 40HQ containers
2200*6600
2600*6000
one 40FR open container and one 40HQ container
2600*6600
2800*6000
2800*6600
 
7.Oil refining machine installation:
We will give the foundation drawings to buyer after make the order .we will send engineer when buyer gets the machine. The engineer mainly installs the machine and trains your workers.
8.Oil refining machine covers area:
The machine itself cover 300 square meters (length 20M, Width 15M)
Add raw material stay, carbon black stay, big oil tank zone, workers rest room and simple office. It takes at least 600-800 square meters.
9.How many workers need operate machine?
4 workers is enough for one set machine. 
10.Delivery time:
We will delivery the machine within 15-20days after get the advance payment (30% of the total amount).
11. Port (China):
Lianyungang port or Qingdao port
12. Warranty and machine life:
We guarantee the complete machine two years, the reactor life more than 4 years, others parts no need change lifelong expect the wearing parts.
13.The warranty and after-service:
1) We will supply the foundation drawings to buyer after get deposit.
2) The delivery time is 15-20 days after get deposit.
3) We will send engineers to install the machine when the machine reach buyer's factory. 
4) We warranty the complete machine two years, we will maintenance all it life. When the machine can not running normal, the buyer can call us, we will help buyer repair it by call, if can not solve, we will send engineer to buyer's factory at the shortest time. If buyers need change parts, you can buy it from our factory.
 
If you are interested in our products,please contact us
when you feel convenient,thanks.