Product Main

Quick Details

Material: Steel
Model Number: M5-M22
Brand Name: SJT
Place of Origin: China (Mainland)
Surface treatment: Blackened or galvanized
hardness: high
Shape: Rectangular or round, arc
Wedge: 2pc 3pc 4pc
Capacity: HRC15-37
Type: One use and re-usable

Specifications


Definition

 

KM anchorage system is a completed, independent building measure researched. It has been widely adoped by modern construction, especially used in pre-tension or post-tension for concrete constructions as building materials. KM Series products are composed of tensioning anchor, holding anchor, connectors. It can be used to lock the steel strand wires on/under clases of 2000MPa standard strength, which is usually in diameters of9.53mm\11.1mm\12.7mm\12.9mm\15.2mm\15.7mm\17.8mm\20.3mm\21.8mm.

 

 

Product details

 

1. Type:KM series, M5-M22
2. Shape: round and flat , from 1 hole to 55holes 
3. Application: concrete works usage

4. Standard: ASTM/BS/JIS/GB/AS

5. Model type for PC strand:

Model#

pC Strand Size

M5,M6,M7

7.0mm, 6.0mm, 5.0mm spiral ribbed pc wire

M10

9.3mm, 9.53mm pc strand;

M11

10.8mm pc strand

M13

12.7mm, 12.5mm & 12.9mm pc strand

M15

15.2 or 15.24mm, 15.7mm

M18

17.8mm pc strand

M22

21.6/21.8mm pc strand 


Instructions

1. YM anchorage must be used with YM working wedge, and YM tool anchorage must be used with YM tool wedge. 


2. Work anchorage can't substitute for tool anchorage. 

3. YM series anchorage must be used with the same specification located plates of YM. 

4. Anchorage must be well keeped to prevent rusting and dirts. Before installation, rusting and dirts must be cleand to prevent from damaging the internal thread of wedge which will fill in the alveolar of wedge when tension. 

5. When install anchorage, O Dia of Anchor Head should put in hole of Anchor Bearing Plate, and the restraing plate must in the same direction with the hole of tool anchorage, and the strands cannot be twined around each other and dislocated.

 

Pre-Stressing Concrete Anchorage Tension Procedure
I  Preparation:  
1) Clean the remained concrete inside of the anchor bearing plate,wipe the strand out of rusty and mud.
2)Install anchorage, wedges and located plate.
II  Location and installment of tension equipments
1) Get the tension jack ready and put in proper location in spot.
2) Install tool anchor,daub lube oil on outside of tool anchor wedges
III. Tension: 
1)Turn on the hydraulic pump supply oil to jack tank slowly, till oil pressure reach up to the set-up value.
 2) Measuring the extension length of the strand.
 3) Make a data record for tension.
IV. Anchoring: 
1) Loose the stop-current valve, let the pressure back to 0 gradually. When the gauge show zero, the anchoring move has been finished. 
2) The pump collects the oil back to return way tank, the piston back to the bottom as beginning..
3) Unload jack and located plate.
IX. Seal the end:
1) Cutting out the over long remaining strand, seal the anchorage with concrete.
2) Grouting the concrete to the corrugated pipe, seal and grouting shall be within 24 hours.